LAMMA POWER STATION EXTENSION

Supply and Installation of Submarine Gas Pipeline

 

 

 

Lamma Water Quality Monitoring During Dredging Works

Monitoring Report

 

March 2005

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

0

4/4/05

Issued for comments

WK

 

 

 

REV

DATE

DESCRIPTION

PREPARED

 CHECKED

APPROVED

PURCHASER

STATUS CODE :  A = Issued for comments – B = Issued for approval – C = Approved for Construction

 

TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN

WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER

                   


                  

THE HONGKONG ELECTRIC CO., LTD.

LAMMA POWER STATION EXTENSION

Supply and Installation of Submarine Gas Pipeline

Contract No. 03/9008

 

 

Doc. No.: LTLD-32-1-138-G

REVISION

0

STATUS

A


TABULATION OF REVISED PAGES

PAGE

REVISIONS

 

PAGE

REVISIONS

 

0

1

2

3

4

5

6

7

0

1

2

3

4

5

6

7

1

 

 

 

 

 

 

 

 

 

51

 

 

 

 

 

 

 

 

 

2

 

 

 

 

 

 

 

 

 

52

 

 

 

 

 

 

 

 

 

3

 

 

 

 

 

 

 

 

 

53

 

 

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

 

 

54

 

 

 

 

 

 

 

 

 

5

 

 

 

 

 

 

 

 

 

55

 

 

 

 

 

 

 

 

 

6

 

 

 

 

 

 

 

 

 

56

 

 

 

 

 

 

 

 

 

7

 

 

 

 

 

 

 

 

 

57

 

 

 

 

 

 

 

 

 

8

 

 

 

 

 

 

 

 

 

58

 

 

 

 

 

 

 

 

 

9

 

 

 

 

 

 

 

 

 

59

 

 

 

 

 

 

 

 

 

10

 

 

 

 

 

 

 

 

 

60

 

 

 

 

 

 

 

 

 

11

 

 

 

 

 

 

 

 

 

61

 

 

 

 

 

 

 

 

 

12

 

 

 

 

 

 

 

 

 

62

 

 

 

 

 

 

 

 

 

13

 

 

 

 

 

 

 

 

 

63

 

 

 

 

 

 

 

 

 

14

 

 

 

 

 

 

 

 

 

64

 

 

 

 

 

 

 

 

 

15

 

 

 

 

 

 

 

 

 

65

 

 

 

 

 

 

 

 

 

16

 

 

 

 

 

 

 

 

 

66

 

 

 

 

 

 

 

 

 

17

 

 

 

 

 

 

 

 

 

67

 

 

 

 

 

 

 

 

 

18

 

 

 

 

 

 

 

 

 

68

 

 

 

 

 

 

 

 

 

19

 

 

 

 

 

 

 

 

 

69

 

 

 

 

 

 

 

 

 

20

 

 

 

 

 

 

 

 

 

70

 

 

 

 

 

 

 

 

 

21

 

 

 

 

 

 

 

 

 

71

 

 

 

 

 

 

 

 

 

22

 

 

 

 

 

 

 

 

 

72

 

 

 

 

 

 

 

 

 

23

 

 

 

 

 

 

 

 

 

73

 

 

 

 

 

 

 

 

 

24

 

 

 

 

 

 

 

 

 

74

 

 

 

 

 

 

 

 

 

25

 

 

 

 

 

 

 

 

 

75

 

 

 

 

 

 

 

 

 

26

 

 

 

 

 

 

 

 

 

76

 

 

 

 

 

 

 

 

 

27

 

 

 

 

 

 

 

 

 

77

 

 

 

 

 

 

 

 

 

28

 

 

 

 

 

 

 

 

 

78

 

 

 

 

 

 

 

 

 

29

 

 

 

 

 

 

 

 

 

79

 

 

 

 

 

 

 

 

 

30

 

 

 

 

 

 

 

 

 

80

 

 

 

 

 

 

 

 

 

31

 

 

 

 

 

 

 

 

 

81

 

 

 

 

 

 

 

 

 

32

 

 

 

 

 

 

 

 

 

82

 

 

 

 

 

 

 

 

 

33

 

 

 

 

 

 

 

 

 

83

 

 

 

 

 

 

 

 

 

34

 

 

 

 

 

 

 

 

 

ATTACHMENTS/APPENDIX 

35

 

 

 

 

 

 

 

 

 

A

 

 

 

 

 

 

 

 

 

36

 

 

 

 

 

 

 

 

 

B

 

 

 

 

 

 

 

 

 

37

 

 

 

 

 

 

 

 

 

C

 

 

 

 

 

 

 

 

 

38

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

39

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

40

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

41

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

42

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

43

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

44

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

45

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

46

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

47

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

48

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

49

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

50

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Saipem Asia Sdn. Bhd

 

 

 

 

 

 

 

 

 

Lamma Power Station Extension

– Supply and Installation

of Submarine Gas Pipeline

 

Lamma Water Quality Monitoring During Dredging Works

Monitoring Report (Version 1.0)

 

March 2005

 

 

 

 

 

Approved By

 

 

(Project Director: Dr. HF Chan)

 

REMARKS:

 

The information supplied and contained within this report is, to the best of our knowledge, correct at the time of printing.

 

CINOTECH accepts no responsibility for changes made to this report by third parties.

 

 

CINOTECH CONSULTANTS LTD

Room 1602-1610, Delta House,

3 On Yiu Street,

Shatin, NT, Hong Kong

Tel: (852) 2151 2083    Fax: (852) 3107 1388

Email: info@cinotech.com.hk

 

 

Table of contents

 

 

 

EXECUTIVE SUMMARY.. 4

Introduction. 4

Environmental Monitoring Works. 4

Complaints and Prosecutions. 4

Future Key Issues. 4

1      INTRODUCTION.. 4

Background. 4

Project Organizations. 4

Construction Programme. 4

Summary of EM&A Requirements. 4

2      Water Quality Monitoring.. 4

Monitoring Requirements. 4

Monitoring Parameters. 4

Monitoring Equipment 4

Monitoring Frequency and Duration. 4

Monitoring Locations. 4

Monitoring Methodology, Calibration Details and QA/QC Procedures. 4

Results and Observations. 4

3      ENVIRONMENTAL AUDIT.. 4

Review of Environmental Monitoring Procedures. 4

Implementation Status of Event Action Plans. 4

Implementation Status of Mitigation Measures. 4

Summary of Non-compliance of the Environmental Quality Performance Limit 4

Summary of Complaints and Prosecution. 4

4      CONCLUSIONS AND RECOMMENDATIONS.. 4

Conclusions. 4

 

 

lIST OF TABLES

 

Table 1.1        Key Project Contacts

Table 2.1        Water Quality Monitoring Parameters

Table 2.2        Water Quality Monitoring Equipment

Table 2.3        Frequency and Parameters of Water Quality Monitoring

Table 2.4        Locations of Water Quality Monitoring Stations

 

 

lIST OF FIGUREs

 

Figure 1          Locations of Water Quality Monitoring Stations

 

 

lIST OF APPENDIces

 

A                      Copy of Calibration Certificate of Monitoring Equipment

B                                    Action and Limit Levels for Water Quality Monitoring

C                                    Water Quality Monitoring Results and the Graphical Presentation(DOSM, DOB, TUR & SS)

D                                    Event Action Plan for Water Quality

E                                    Monitoring Schedule

F                                     Construction Phase Mitigation Measures and their Implementation (Gas Pipeline)

G                                    Complaint Log

 

 


List of Abbreviation

 

 

DO

Dissolved Oxygen

EIA

Environmental Impact Assessment

EM&A

Environmental Monitoring and Audit

ET

Environmental Team

GPS

Global Positioning System

GRS

Gas Receiving Station

HEC

Hong Kong Electric Co. Ltd

HOKLAS

The Hong Kong Laboratory Accreditation Scheme

LNG

Liquefied Natural Gas

QA/QC

Quality Assurance / Quality Control

SS

Suspended Solids

                       

 

 

 


EXECUTIVE SUMMARY

Introduction

 

1.        This is the second Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited (ET-Cinotech) for the dredging works at the Lamma Shore Approach (approximately 0.7km) for the project “Lamma Project Station Extension – Supply and Installation of Submarine Gas Pipeline” (the Project).  This document reported the findings of EM&A Works conducted in March 2005.

Environmental Monitoring Works

 

2.        Environmental monitoring for the Project was performed as stipulated in the Work Procedure and the results were checked and reviewed. 

 

3.        Summary of the non-compliance of the monitoring events is tabulated Table I.

 

Table I      Summary Table for Non-compliance Recorded

Media /

Nature

No. of Exceedances

Action Taken

Results of action taken

Remarks

Action Level

Limit Level

DO

0

0

N.A.

N.A.

-

Turbidity

0

0

SS

0

0

 

Water Quality

 

4.        Water quality monitoring was conducted as scheduled for 3 days a week in the first stage, i.e., within the first two weeks of the dredging works at Lamma Approach.  As the monitoring results in the first stage were found to be acceptable (no exceedance of water quality related to the Project), the frequency of the monitoring was reduced to 1 day within the third and fourth weeks of the dredging works, i.e., the second stage.  Since the monitoring results obtained in second stage are found to be acceptable, further monitoring was not necessary.

 

5.        There was no exceedance for all the parameters.  No major pollution sources were identified during the monitoring. 

 

Complaints and Prosecutions

 

6.        No environmental complaint and prosecution were received during the reporting month.

Future Key Issues

 

7.        The dredging works were completed on 13th March 2005. No key environmental issue was identified for the coming month.

 

 


1               INTRODUCTION

Background

1.1        Hong Kong Electric Holdings Ltd. (HEC) intends to develop a 1,800 MW power station in Hong Kong Special Administrative Region (HKSAR) to meet the forecast increase in electricity demand to cope with the social and economical growth of the HKSAR. The proposed power station will be located at reclaimed land in the south of the existing Lamma Power Station at the western edge of Lamma Island, termed Lamma Power Station Extension.

1.2        The proposed Power Station will use natural gas as fuel to generate electricity. The natural gas will be supplied from Guandong Liquefied Natural Gas (GD LNG) Terminal located at Cheng Tou Jiao of Shenzen PRC via a 20 inches diameter gas submarine pipeline. 

1.3        HEC awarded Saipem Asia Sdn. Bhd. (hereafter called “the Contractor) for the design, engineering, supply of materials, fabrication, testing at works, delivery to site, complete erection including pre-trenching, pipe laying, rock dumping, testing and pre-commissioning at site, preservation during the Defects Liability Period of Submarine Gas Pipeline under to Project titled “Lamma Power Station Extension – Supply and Installation of Submarine Gas Pipeline” (hereinafter called “the Project”). Cinotech Consultants Limited was subsequently commissioned by the Contractor as the Environmental Team (ET-Cinotech) to provide environmental consultancy services and to undertake the Environmental Monitoring and Audit (EM&A) works for the Project.

1.4        The Project works include Pre-Trenching works, Pipe-Lay installation, Post-Lay Trenching (Jetting) and Rock Dumping works related to the installation of 92 km of 20 inches diameter Submarine Gas Pipeline between Guandong Liquefied Natural Gas Terminal (GD LNG) and the receiving point at Gas Receiving Station (GRS) at South-West of Lamma Extension on Lamma Island of Hong Kong – SAR.  

1.5        In particular, trench dredging works are carried out at the Lamma Shore Approach (approximately 0.7 km) for a period of about 45 days and the location is also shown in Figure 1.  According Item 4.5 of the “Response to Tenderers’ Query No.2”, a minimum of ten (10) water quality monitoring stations for the dredging works at Lamma shore approach. 

1.6        A Work Procedure outlining the monitoring and audit programme to be undertaken for the pre-trenching (dredging) works for the Lamma Shore Approach was submitted and approved.  The dredging works and the corresponding monitoring works in accordance with the Work Procedure were commenced on 22nd February 2005. The dredging works were completed on 13th March 2005 whist the monitoring works were finished on 15th March 2005.

 

Project Organizations

1.7        Different parties with different levels of involvement in the project organization include:

·       Project Proponent –Hong Kong Electric Holdings Ltd. (HEC)

·       Contractor – Saipem Asia Sdn. Bhd.

·       Environmental Team (ET-Cinotech) – Cinotech Consultants Limited

 

1.8        The responsibilities of respective parties are detailed in Section 3 of the EM&A Requirements Review (Review) and the project organization chart is presented in Figure 3.1 of the Review. The key contacts of the ET- Cinotech are shown in Table 1.1.

Table 1.1                       Key Project Contacts

Party

Name

Role

Phone No.

Fax No.

ET-Cinotech

Dr. Priscilla Choy

Project Manager of ET

2151 2089

3107 1388

Ms. Winniss Kong

Coordinator

2151 2068

3107 1388

Mr. Henry Leung

Monitoring Team Leader

2151 2087

3107 1388

 

Construction Programme

1.9        The dredging works for Lamma Shore Approach were commenced on 22nd February 2005 and were completed on 13th March 2005. 

Summary of EM&A Requirements

1.10    The EM&A programme requires water quality during the dredging works of the Lamma Shore Approach.  Full scale water quality monitoring will be carried out within the first two weeks of the construction programme.  The frequency of the monitoring after the initial two weeks will then be reduced if no acceptable impact is revealed.

1.11    The EM&A requirements are described in following sections, including:

·       All monitoring parameters;

·       Statutory limits for all environmental parameters;

·       Event / Action Plan.

1.12    This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the required monitoring parameters, namely water quality for the dredging works of the Lamma Shore Approach.


2               Water Quality Monitoring

Monitoring Requirements

2.1        In order to ensure that any deterioration in water quality can be readily detected and timely action taken to rectify the situation, a water quality monitoring programme is required.

2.2        Monitoring should be carried out in stages:

1.      First Stage: 3 days a week within the first two weeks of the dredging works at Lamma Approach.  The monitoring shall be conducted on non-consecutive days.

2.      Second Stage: If the monitoring results in first stage are found to be acceptable (no exceedance of water quality related to the Project), the frequency of the monitoring will be reduced to 1 day within the third and fourth weeks of the dredging works, subject to the approval of HEC. 

3.      Final Stage: If the monitoring results obtained in second stage are found to be acceptable, the monitoring will then cease, subject to the approval of HEC.

Monitoring Parameters

2.3        The following water quality parameters were included in the monitoring programme.

Table 2.1     Water Quality Monitoring Parameters

Phase

Water Quality Parameters

Construction

·    Temperature (oC)

·    Salinity (ppt)

·    pH (pH value)

·    Turbidity (NTU)

·    Dissolved oxygen (DO) (mg/L and % of saturation)

·    Suspended solids (SS) (mg/L)

 

Monitoring Equipment

2.4        The water sampler used for water quality monitoring was Kahlsico Water-Bottle Model 135DW150.  The sampler with associated equipment complied with the specifications stipulated in the Work Procedure.

2.5        Table 2.2 summarizes the equipment used in the water quality monitoring program.  All the monitoring equipment complied with the specifications stipulated in the Work Procedure.  Copies of the calibration certificates of are attached in Appendix A.

Table 2.2     Water Quality Monitoring Equipment

Equipment

Model and Make

Qty.

Water Sampler

Kahlsico Water-Bottle Model 135DW 150

1

Multi-parameter Water Quality System

YSI 6820

2

Monitoring Position Equipment

“Magellan” Handheld GPS Model GPS-320

1

 

 

Monitoring Frequency and Duration

2.6        Table 2.3 summarizes the monitoring period and frequencies of water quality monitoring.

Table 2.3     Frequency and Parameters of Water Quality Monitoring

Station

Parameters

Frequency

No. of depth

C2, C4, C5, SR1, SR2, SR3, SR4, SR5, SR6 and SR7

SS, turbidity, DO and in-situ parameters*

3 times a week within the first two weeks of the dredging works, reduced to once a week in the third and fourth week if no exceedance recorded

3

Notes:

*   In-situ parameters included temperature, pH, salinity and DO saturation.

Monitoring Locations

2.7        A total of ten water quality monitoring locations were selected.  Table 2.4 describes the locations of these monitoring stations.  The locations of the control and impact monitoring stations are shown in Figure 1.


Table 2.4  Locations of Water Quality Monitoring Stations

Station

HK 1980 Grid

Easting

Northing

Control

 

 

C2

828608

813492

C4

826776

806464

C5

830440

802186

Impact

 

 

SR1

830224

811528

SR2

829004

810903

SR3

829194

808600

SR4

830119

808650

SR5

830386

807189

SR6

829977

805758

SR7

829566

804545

Monitoring Methodology, Calibration Details and QA/QC Procedures

Instrumentation

2.8        A multi-parameter meter (Model YSI 6820 CE-C-M-Y) was used to measure DO, turbidity, salinity, pH and temperature.

Operating/Analytical Procedures

2.9        At each measurement, two consecutive measurements of in-situ parameters were taken.  The probes were retrieved out of the water after the first measurement and then re-deployed for the second measurement.  Where the difference in the value between the first and second readings of each set was more than 25% of the value of the first reading, the reading was discarded and further readings were taken.

2.10    For SS measurement, grab samples were collected.  Water samples of about 1,000 ml were collected and stored in polyethylene bottles.  The sample bottles were packed into an ice-box and delivered to a HOKLAS Laboratory, WELLAB Ltd., for the analysis within 24 hours.

Maintenance and Calibration

2.11    Before each round of monitoring, a zero check in distilled water was performed with the turbidity probe of YSI 6820.  The probe was kept in wet condition and then calibrated with a solution of known NTU.

Results and Observations

2.12    The monitoring results and the graphical presentation are shown in Appendix C.  Note that in Appendix C, the “sea condition” is given as indicative information and does not necessarily adhere to any standard sea state descriptions.  In general, “calm” means small or no waves were observed; “rough” includes white-capped sea or rougher; and “moderate” means all conditions in between “calm” and “rough”.

2.13    Water quality monitoring was conducted on 1st, 3rd, 5th, 8th and 15th March 2005 in both mid-ebb and mid-flood tides while dredging works were taking place as per the monitoring schedule (Appendix E).

2.14    The weather during the monitoring session was sunny, cloudy or fine. 

2.15    The results from the impact monitoring stations were compared with that of the control stations.  The Action / Limit Levels for the water quality monitoring are summarized in Appendix B.

2.16    No exceedances for DO, turbidity and SS concentrations were recorded at the impact monitoring stations.  The monitoring data of the impact monitoring stations were comparable to that of the control stations.  Further water quality monitoring was not necessary.

2.17    No major pollution source was observed. 


3               ENVIRONMENTAL AUDIT

Review of Environmental Monitoring Procedures

3.1        The monitoring works conducted by the monitoring team were inspected.  The following observations have been recorded for the monitoring works:

·       The monitoring team recorded all observations around the monitoring stations, which might affect the monitoring result.

·       The monitoring team recorded the weather and sea conditions on the monitoring day.

Implementation Status of Event Action Plans

3.2        The Event Action Plan for water quality is presented in Appendix D.  No exceedance was recorded in the monitoring event.  No further action/ monitoring was required.

Implementation Status of Mitigation Measures

3.3        The implementation status of mitigation measures is summarized in Appendix F.

Summary of Non-compliance of the Environmental Quality Performance Limit

3.4        No non-compliance was recorded during the site audits in the reporting month. 

Summary of Complaints and Prosecution

3.5        No environmental complaint and prosecution was received during the reporting month.  The complaint log for the works is provided in Appendix G.


4               CONCLUSIONS AND RECOMMENDATIONS

Conclusions

4.1        Environmental monitoring works were performed on 1st, 3rd, 5th, 8th and 15th March 2005 in accordance with the Work Procedure while dredging works were undertaking.  All monitoring results were checked and reviewed.

4.2        There was no Action/Limit Level exceedance for all the water quality parameters.  No major pollution sources were identified.  Further monitoring was not necessary.

4.3        The dredging works were completed on 13th March 2005. No key environmental issue was identified for the coming month.